Issue - meetings

Revenue and Capital Monitoring 2018/19 as at 30th September 2018

Meeting: 29/11/2018 - CPH Transport & Highways Decision Session (Item 5.)

5. Revenue and Capital Monitoring 2018/19 as at 30th September 2018 pdf icon PDF 130 KB

To inform the Cabinet Member of the Portfolio’s latest forecast financial position as at the 30th September 2018 against Revenue and Capital budgets as summarised below and detailed in the attached Appendix A.

To inform the Cabinet Member of the Portfolio’s progress against the latest 3 year savings targets in the Medium Term Financial Strategy (MTFS) summarised below and detailed in Appendix A.

To inform the Cabinet Member of the Portfolio’s future pressures and mitigations detailed in Appendix B.

Additional documents:

Decision:

The Cabinet Member:

1.  Considered and endorsed the 2018/19 revenue and capital financial monitoring forecast as at 30th September 2018;

2.  Considered the Portfolio’s progress against the latest 3 year savings targets in the Medium Term Financial Strategy (MTFS) as at 30th September 2018; and

3.  Approved the £1.161m addition to the capital programme as per paragraph 3.7 of the report.